B-183620 1 (1975-07-10)

handle is hein.gao/gaobadcfz0001 and id is 1 raw text is: 



                             THE  COMPTROLLER GENERAL
  DE CISION                  OF   THE UNITEO STATES
                             WASHINGTON, D.C. 20548




FILE:    B-183620                   DATE:  July 10,1975

MATTER OF:        Pak/Master, Inc.


DIGEST:

   Where prices quoted in bid by contractor for additional
   quantities  (contract option) were based upon same unit
   rates as basic quantities, whereas solicitation indicated
   that additional rates were to be exclusive of preliminary
   costs, but contracting officer in making award accepted
   bidder's quotation which included prices for basic and
   additional quantities, prices should have been reviewed to
   ascertain compliance with bidding requirement which would
   have furnished notice of error; therefore, request for
   contract adjustment is sustained.

     Invitation for bids for Jacket 567-133 was issued by the
Government Printing Office for the production of 14,000 each of
three separate printed, die-cut/scored mailing boxes, plus 42,000
unprinted die-cut outer shipping containers for the Postal Service.
Two bids were received:  one for $24,846.80 from Mack Allied Corp.
and the other from Pak/Master, Inc., for $20,202. The contract was
awarded to Pak/Master on February 10, 1975, for delivery on March 28,
1975.  After award, Pak/Master alleged that it made an error in bid
in that it inadvertently omitted a one-time charge of $1,473.90 for
dies and it requested a contract adjustment for the omission.

     With regard to mistakes alleged after the award of a contract,
the general rule is that the bidder must bear the consequences of
the mistake unless the contracting officer .lnew or should have
known of the probability of mistake at the time the bid was
accepted.  Wender Presses, Inc. v. United States, 343 F.2d 961
(Ct. Cl. 1965); Saligman v. United States, 56 F. Supp. 505 (E.D.
Pa. 1944); and 45 Comp. Gen. 305 (1965).

     In this case the contracting officer did not seek verification
of Pak/Master's $20,202 bid because the estimate of the Postal Service
was $20,000.  Nevertheless, GPO Counsel contends that the contracting
officer was on constructive notice of error, since the prices quoted
by Pak/Master for additional quantities, if produced at the same
time as the initial order, were based upon the same unit rates as
the basic quantities whereas the terms of the solicitation required
the exclusion of all preliminary costs from the prices for the
additional quantities.


- 1 -

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most