B-179026 1 (1974-01-25)

handle is hein.gao/gaobadcbq0001 and id is 1 raw text is: 




*-~ A


FILE:  B-179026


   '~  ~ THE COMPTROLLER   GE1'JEIRAL
   (. 7d'OF   THE UNITED  STATES
V    -   :  WASHINGTON, D.C. 20548




                   DATE:    January 25, 1974


MATTER OF: Harper Enterprises


DIGEST:


Where bidder denied a certificate of competency
by Small Business Administration (SBA) while bid-
der had just 2 days prior to denial entered into
a joint venture agreement to obtain necessary
resources to perform, and where contracting offi-
cer's attempted rereferral to SBA not accepted
since SBA questioned responsiveness of bid vis-
a-vis joint venture and SBA also indicated that no
new evidence had been produced; notwithstanding
fact that SBA stated bidder could possibly per-
form if joint venture allowed, contracting offi-
cer should not have ignored joint venture agree-
ment in determining responsibility of bidder and
joint venture agreement should be reassessed to
determine responsibility of bidder.


               Award for continuing services to incumbent con-
               tractor during pendency of protest was not inapcro-
               priate since it did not deprive protesting bidder
               of contract in that agency has indicated it ..ill
               terminate awarded contract for convenience of
               Government and make award to protesting bidder if
               protest is sustained.


     Invitation for bids (IFB) No. DAHC23-73-B-OOh8 was issued by the
Military Traffic  Management and Terminal Service on May 25, 1973. The
subject IFB sought to procure janitorial services to be performed at
the Oakland Army Base, Oakland, California, and Fort Mason in San Fran-
cisco, California.

     Award of the schedule B (Fort M1ason) portion of the IFB has been
awarded to the Dependable Janitorial Service (Dependable) pursuant to a
schedule severability provision in the solicitation and Harper does not
question this award.  However, Harper does question the agency's actions
with regard to schedule A (Oakland Army Base). Schedule A of the
IFB was awarded to the second low bidder (Dependable) prior to our
issuance of a decision since the Army made a determination per ASPR 2-
407.8(b)(3)(iii) in that prompt award would be advantageous to the
Government.               &qz       /DV7?7F

     Harper, the apparent low bidder on schedule A, submitted a bid
which gave rise to a contention by Dependable that Harper's responsibility


                                                       53 Comp. G

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most