B-405082.2 1 (2011-07-27)

handle is hein.gao/gaobadbxg0001 and id is 1 raw text is: 



L         G     A   O                                                    Comptroller General
        Accountability * Integrity * Reliability                          of the United States
United States Government Accountability Office  DOCUMENT FOR PUBLIC REEASE
Washington, DC 20548                                  The decision issued on the date below was subject to
                                                      a GAO Protective Order. This redacted version has
                                                      been approved for public release.

          Decision

          Matter of:   STG,  Inc.

          File:        B-405082;  B-405082.2

          Date:        July 27, 2011

          Claude  P. Goddard Jr., Esq., Daniel J. Donohue, Esq., and Sarah M. Graves, Esq.,
          Husch  Blackwell LLP, for the protester.
          Fernand  A. Lavallee, Esq., Seamus Curley, Esq., Dionis M. Gauvin, Esq., DLA Piper
          LLP  (US), for Aquilent, Inc., an intervenor.
          Frank V. DiNicola, Esq., Kim J. Sawicki, Esq., and Tiffany N. Alford, Esq.,
          Department  of Veterans Affairs, for the agency.
          Linda C. Glass, Esq., and Sharon L. Larkin, Esq., Office of the General Counsel,
          GAO,  participated in the preparation of the decision.
          DIGEST

          Protest of 4-month sole-source task order for interim services placed against Federal
          Supply Schedule  (FSS) contract is denied where the services were urgently required
          and agency  reasonably concluded that following the applicable FSS competitive
          ordering procedures would result in unacceptable interruptions of service.
          DECISION

          STG,  Inc., of Reston, Virginia, protests the Department of Veterans Affairs (VA)
          issuance of a 4-month task order to Aquilent, Inc., of Laurel, Maryland, for
          maintenance  and support services for the VA's Electronic Contract Management
          System  (eCMS).

          We  deny the protest.

          The  eCMS  is an electronic data management system that houses all the VA's
          procurement  and contracting data and provides the agency with reporting on
          procurement  and contracting activities. Contracting Officer's Statement at 1. The
          eCMS   is a nationwide system that electronically manages the creation, storage, and
          security of VA's procurement actions. Id.

          This protest follows an earlier protest by STG, objecting to the issuance of a task
          order to Aquilent, the incumbent, for services to develop, support, and maintain

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most