B-401871.5,B-401871.6,B-401871.7 1 (2010-05-24)

handle is hein.gao/gaobadbij0001 and id is 1 raw text is: 




         G     A    0                                                 Comptroller General
       Accountability * Integrity * Reliability                       of the United States
United States Government Accountability Office        DOCUMENT   FOR PUBLIC  RELEASE
Washington, DC 20548                                 The decision issued on the date below was subject to a
                                                     GAO Protective Order. This redacted version has been
                                                     approved for public release.

          Decision

          Matter of:  Contrack International, Inc.

          File:       B-401871.5, B-401871.6, B-401871.7

          Date:       May  24, 2010

          Kevin P. Connelly, Esq., Joshua C. Drewitz, Esq., and Amanda B. Weiner, Esq.,
          Seyfarth Shaw LLP, for the protester.
          Sam Z. Gdanski, Esq., Gdanski & Gdanski, LLP, for Zafer Contracting Construction
          and Trade Company., Inc., the intervenor.
          Jeremy Becker-Welts, Esq., and Patrick D. Bowman, Esq., Department of the Army,
          Corps of Engineers, for the agency.
          Linda C. Glass, Esq., and Guy R. Pietrovito, Esq., Office of the General Counsel, GAO,
          participated in the preparation of the decision.
          DIGEST

          Protest that the agency's evaluation of the awardee's past performance was
          unreasonable is sustained where the agency did not consider relevant adverse
          information, of which the agency was aware, for the awardee.
          DECISION

          Contrack International, Inc., of McLean, Virginia, protests the award of a contract to
          Zafer Contracting Construction and Trade Company, Inc., of Ankara, Turkey, under
          request for proposals (RFP) No. W917PM-09-R-0075, issued by the Department of the
          Army, Corps of Engineers, for the design and construction of an ammunition supply
          point at Bagram Airfield, Afghanistan. The protester challenges the agency's
          evaluation of proposals and source selection decision.

          We sustain the protest.

          BACKGROUND

          The RFP, issued on May 25, 2009, provided for the evaluation of proposals on a best
          value basis under the following factors, listed in descending order of importance:
          experience, past performance, project management plan and price. Offerors were
          informed that the non-price evaluation factors combined were equal to price. RFP
          at 22-24.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most