B-311000.2,B-311000.3,B-311000.4 1 (2008-11-10)

handle is hein.gao/gaobadauz0001 and id is 1 raw text is: 




         G     A     0                                                 Comptroller General
       Accountability * Integrity * Reliability                         of the United States
United States Government Accountability Office      DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                  The decision issued on the date below was subject to a
                                                      GAO Protective Order. This redacted version has been
                                                      approved for public release.

          Decision

          Matter  of:  Blackwater Lodge  and Training Center, Inc.

          File:        B-311000.2; B-311000.3; B-311000.4

          Date:        November  10, 2008

          Robert E. Korroch, Esq., and Francis E. Purcell, Esq., Williams Mullen, for the
          protester.
          William W. Goodrich, Esq., Lisa K. Miller, Esq., and Kavitha Babu, Esq., Arent Fox,
          LLP, for Automation Precision Technology, Inc., an intervenor.
          Sharon H. Sachs, Esq., Department of the Navy, for the agency.
          Mary G. Curcio, Esq., and John M. Melody, Esq., Office of the General Counsel, GAO,
          participated in the preparation of the decision.
          DIGEST

          1. Protest that agency's assigning protester's and awardee's technical proposals
          same evaluation rating was unreasonable where protester, but not awardee, offered
          to provide all training at its own facility within desired driving distance is denied,
          where protester's proposal was credited with strength on this basis, and evaluation
          rating was not based solely on ownership and location of facility.

          2. Protest that agency's evaluation unreasonably failed to take into account alleged
          safety concerns arising in connection with awardee's performance under prior
          contracts is denied where agency was aware of and considered safety concerns, but
          determined that awardee had adequately addressed the concerns during
          performance of the contracts.
          DECISION

          Blackwater Lodge and Training Center, Inc., of Moyock, North Carolina, protests the
          award of a contract to Automation Precision Technology, Inc. (APT), of Norfolk,
          Virginia, under request for proposals (RFP) No. N61339-07-R-0039, issued by the
          Department  of the Navy for a contractor to provide a training program for small
          arms live fire. Blackwater argues that the agency improperly evaluated APT's
          technical capability and past performance.


We  deny the protest.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most