B-292178,B-292178.2,B-292178.3 1 (2003-07-17)

handle is hein.gao/gaobacylq0001 and id is 1 raw text is: 


   Il
   im

         G    A     0Comptroller General
 .   . Accountability * Integrity Reliability                        of the United States
United States General Accounting Office              DOCUMENT   FOR PUBLIC RELEASE
Washington, DC 20548                                The decision issued on the date below was subject to a
                                                    GAO Protective Order. This redacted version has been
                                                    approved for public release.

         Decision

         Matter  of:  Cortez, Inc.

         File:        B-292178; B-292178.2; B-292178.3

         Date:        July 17, 2003

         Kenneth M. Bruntel, Esq., Daniel R. Forman, Esq., Amy E. Laderberg, Esq., and
         Michael Abelow, Esq., Crowell & Moring, for the protester.
         Mark  D. Colley, Esq., David S. Black, Esq., Stuart W. Turner, Esq., Caitlin K. Cloonan,
         Esq., and Michele M. Brown, Esq., Holland & Knight, for EG&G Technical Services,
         Inc., an intervenor.
         Sumara  M. Thompson-King, Esq., and Jerry L. Seemann, Esq., National Aeronautics
         &  Space Administration, for the agency.
         David A. Ashen, Esq., and John M. Melody, Esq., Office of the General Counsel, GAO,
         participated in the preparation of the decision.
         DIGEST

         1. Protest challenging conduct of price realism evaluation and agency determination
         that awardee's pricing was realistic is denied where protester does not show that
         awardee's pricing was likely to result in significant performance risk and agency
         reasonably found that nothing in awardee's pricing called into question its
         understanding of the performance requirements set forth in the solicitation.

         2. Protest that agency unreasonably found awardee's past performance/experience
         superior to the protester's (the incumbent contractor), is denied where, although
         both firms were reported to have strong performance on a number of contracts, and
         protester was given evaluation credit for experience on the incumbent contract,
         agency determined, and protester conceded during discussions, that protester had
         encountered problems in performing the incumbent contract.
         DECISION

         Cortez, Inc. protests the National Aeronautics & Space Administration's (NASA)
         issuance of an order to EG&G Technical Services, Inc., under request for quotations
         (RFQ)  No. 8-1-1-A4-00155, for logistics services at NASA's George C. Marshall Space
         Flight Center (MSFC) in Alabama. The order was issued to EG&G under the General
         Services Administration's LOGWORLD  Federal Supply Schedule. Cortez challenges
         numerous  aspects of the technical and price evaluation.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most