About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline

B-292342 1 (2003-08-22)

handle is hein.gao/gaobacykq0001 and id is 1 raw text is: 


   I

         G     A     0                                                 Comptroller General
 ....Accountability * Integrity * Reliability                           of the United States
United States General Accounting Office                DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                  The decision issued on the date below was subject to a
                                                      GAO Protective Order. This redacted version has been
                                                      approved for public release.

          Decision

          Matter  of:  R&D  Maintenance Services, Inc.

          File:        B-292342

          Date:        August 22, 2003

          Alan M. Grayson, Esq., Brian T. Scher, Esq., and James A. McMillan, Esq., Grayson,
          Kubli & Hoffman, for the protester.
          James R. Thornton, Jr., Esq., and Connie Ledford Baran, Esq., Department of the
          Army, Corps of Engineers, for the agency.
          Kenneth L. Kilgour, Paul I. Lieberman, Esq., and Michael R. Golden, Esq., Office of
          the General Counsel, GAO, participated in the preparation of the decision.
          DIGEST

          1. Allegation that technical evaluation was improper is denied where the record
          establishes that the evaluation was reasonable and consistent with the solicitation
          criteria.

          2. Agency is not required to address offeror's relatively high proposed cost during
          discussions where the cost is not considered unreasonable or unacceptable for
          award.

          3. Protest that awardee engaged in bait and switch is denied where there is no
          allegation that specific key personnel were proposed and evaluated but not provided;
          in the circumstances here, the allegation that the awardee may subcontract certain
          work which it proposed to perform itself does not provide a valid basis for a bait
          and switch allegation.
          DECISION

          R&D  Maintenance Services, Inc. (R&D) protests the award of a cost-plus contract to
          Ferguson-Williams, Inc. (FW) under request for proposals (RFP) No. DACW21-02-R-
          0005, issued by the United States Army Corps of Engineers for certain power plant
          and dam maintenance  and construction work. R&D  initially protested that the Corps
          failed to evaluate proposals in accordance with the RFP criteria and failed to
          conduct meaningful discussions. In response to the agency report, R&D added
          allegations that the awardee engaged in prohibited bait and switch practices and
          that the agency's evaluation was unreasonable.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most