About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline

IMTEC-85-5 1 (1985-03-14)

handle is hein.gao/gaobabnpl0001 and id is 1 raw text is: 

               UlUNITED STATES GENERAL ACCOUNTING OFFICE       /2.bG3
      ]                        WASHINGTON. D.C. 20548


INFORMATION MANAGEMENT
& TECHNOLOGY DIVISION



     B-217586                    126430                 MARCH 14,1985

     The Honorable William E. Dannemeyer

     House of Representatives

     Dear Mr. Dannemeyer:

          Subject: SSA's Acceptance Testing of a Mass Storage
                     System for Computerized Data Was Adequate
                     (GAO/IMTEC-85-5)

          In response to your July 27, 1984, request (see encl. IV), we
     are providing you information on a contract (No. 600-84-0046) the
     Social Security Administration (SSA) awarded to the Masstor Systems
     Corporation for a mass storage system for computerized data. You
     expressed concern that SSA's acceptance testing of the Masstor sys-
     tem had been repeatedly postponed and that SSA may have overlooked
     significant mnandatory contract requirements. Specifically, you
     asked us to observe the acceptance test to make sure mandatory
     requirements were not waived.

          SSA received two responses--one from the Braegen Corporation,
     the other from Masstor--to its July 1983 request for a mass storage
     system. On January 25, 1984, a $1.02 million contract was awarded
     to Masstor, the lowest bidder. We found that during the procure-
     ment process, SSA waived a channel cable length specification that
     it no longer needed.   In waiving this requirement, SSA was within
     the boundaries of federal procurement regulations. Also, shortly
     after the contract was signed, Masstor and SSA disagreed over the
     interpretation of a clause in the contract which, according to SSA,
     specified that Masstor must provide dual-channel access to four of
     SSA's computers. Acceptance testing of the Masstor equipment,
     which was supposed to begin in April 1984, was delayed for 4 months
     while both parties worked to resolve this issue. Masstor eventu-
     ally agreed to install additional equipment, and acceptance testing
     began. We believe this testing--which lasted from August 6 to
     October 8, 1984--provided reasonable assurance that the Masstor
     system met SSA's needs as expressed in the contract.

          Currently, Masstor has a $428,707 claim against SSA for com-
     pensation for extra equipment provided to resolve the above issue.
     Also, SSA has assessed Masstor with $99,665.28 in liquidated
     damages for a 121-day installation delay.

          Details of our review follow.


                                                         (510079)
                          031%41

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most