                  UNITED STATES GENERAL ACCOUNTING OFFICE
                          WASHINGTON, D.C. 20548


PROCUE% ENT AND SYSTEMS
  ACQU1ITION DIVISION


      B-163058                                      JUNE 25, 1979

      The Honorable Harold Brown
      The Secretary of Defense

            Attention: Assistant for Audit Reports
                        Room 3A336
                        ASD (Comptroller)

       Dear Mr. Secretary:

            During calendar year 1978, we reviewed (and individually
       reported on) the military services' development test and
       evaluation (DT&E) of six weapon systems totaling an estimated
       $12 billion in development and procurement costs. (See
       enc. I.) This letter brings to your attention problems
       that, in our opinion, are common to all programs reviewed
       and require your attention for their resolution.

            In general, our review showed that as the design and
       development phase progressed, the six programs experienced
       cost growth, schedule slippages, and performance degra-
       dation problems. To offset some of the increased cost and
       schedule slippages, the agencies responsible for developing
       the systems, without formally assessing risks and benefits,
       (1) reduced the scope of (and hariware for) DT&E during
       critical system and subsystem tests, (2) advanced programs
       into operational testing and production before the completion
       of DT&E on the basis that problems noted could be better
       handled later in the acquisition cycle, and (3) approved
       concurrent production and development.

            In five of the six programs, planned tests resolving
       technical uncertainties affecting mission success (battle
       outcomes) either were reduced or not performed without
       any formal or clear assessment of the risks involved.
       Also, final test reports either were not availaole or
       did not state the critical issues to be resolvec before
       a given stage of development coulo c   considered success-
       fully demonstrated or completed.

                                                 /    PSAD-79-86
                                   (                  (957?C6)


                                   54-.77

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most