About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline

1 1 (November 29, 2016)

handle is hein.crs/govcewy0001 and id is 1 raw text is: 





FF.      '                   riE S-' $. h ,,,. ,


                                                                                                 November 29, 2016

Army Corps Permits for Oil and Natural Gas Pipelines


The U.S. Army Corps of Engineers (the Corps) administers
a regulatory program that requires permits for certain
activities in waters of the United States, including wetlands.
Under Section 404 of the Clean Water Act (CWA, 33
U.S.C. §1344), the Corps regulates the discharge of dredged
or fill material into these waters. Under Section 10 of the
Rivers and Harbors Act (RHA, 33 U.S.C. §403), the Corps
regulates structures and/or work in or affecting the course,
condition, or capacity of navigable waters.

Because construction of pipelines of any significant length
will cross or otherwise affect U.S. waters somewhere along
their routes, the Corps is usually involved in approving
discrete aspects of pipeline siting. The Corps is not the only
governmental agency from which location-specific permits
may be required for a new pipeline, but its role has received
scrutiny recently, particularly in connection with
controversy over siting of the Dakota Access Pipeline
(DAPL). (See CRS Insight IN10567, Dakota Access
Pipeline: Siting Controversy, by Paul W. Parfomak.)


Pipeline construction and other activities that require Corps
authorization and that are similar in nature with minimal
environmental impacts (e.g., minor stream crossings) may
qualify for a general permit. Nationwide permits, which
cover a wide range of activities such as aids to navigation,
minor dredging, and bank stabilization, are one type of
general permit. Some general permits apply regionally or in
a single state. General permits essentially preauthorize a
group of similar activities on a programmatic level. The
Corps uses general permits to minimize the burden of its
regulatory program; general permits authorize applicants to
proceed without the more time-consuming need to obtain
standard individual permits in advance. Individual permits
are subject to public notice, public interest review, public
hearing, activity-specific environmental documentation, and
case-by-case evaluation, so they typically require more time
before an activity is authorized. Over 97% of the Corps'
regulatory workload which averages about 63,000
authorized activities each year-is processed in the form of
general permits.

Many activities covered by nationwide permits can proceed
without advance notification to the Corps, while others
require that the applicant submit a Pre-construction
Notification (PCN) to the Corps and receive written
verification from the Corps before proceeding. Nationwide
permits are issued for five-year terms; the Corps' authority
to issue them expires unless they are reissued. The current
permits were issued in 2012 and will expire in March 2017;
in June 2016, the Corps proposed to reissue the nationwide
permits. (For background, see CRS Report 97-223, The
Army Corps of Engineers'Nationwide Permits Program:
Issues and Regulatory Developments.)


One of the current nationwide permits, NWP 12, is used to
authorize utility line activities, including the construction,
maintenance, or repair of utility lines in waters of the
United States. Under this permit, a utility line is defined
as any pipe or pipeline for the transportation of any
gaseous, liquid, liquescent, or slurry substance, for any
purpose including oil or natural gas and any cable, line,
or wire for the transmission for any purpose of electrical
energy, telephone, and telegraph messages, and radio and
television communication.

Under the CWA and the RHA, the Corps' regulatory
authority only applies to areas where a pipeline or other
utility line activity crosses waters of the United States. The
Corps generally does not have regulatory jurisdiction over
portions that cross upland areas. As a result, for many
pipelines, the Corps has jurisdiction over a very small
portion of the overall pipeline.

When the Corps proposes to reissue the nationwide permits,
as it did in June 2016, the rulemaking process concludes
with Decision Documents that incorporate analytic
requirements under the National Environmental Policy Act
(NEPA). In the Decision Document for NWP 12, the Corps
estimates that NWP 12 is used on average approximately
14,000 times per year on a national basis, resulting in
impacts to approximately 1,750 acres of waters of the
United States, including wetlands that are regulated under
the CWA. (The total includes about 11,500 times per year
for activities that involve a PCN to the Corps and about
2,500 that do not require a PCN.)

The 14,000 number includes all utility line activities that
are authorized by NWP 12. Because of the broad definition,
oil or natural gas pipelines are only a part of the total. The
Corps' data do not break out pipelines versus other types of
utility line activities under NWP 12. Furthermore, while it
covers the large majority of utility line activities, some do
not qualify for a nationwide permit generally because
they will have more than minimal environmental impacts
and thus they must be authorized by individual Corps
permits. The Corps does not have a centralized database or
other information on the number of individual permits that
it issues for pipelines or the number of pipeline and utility
line activities that are authorized by NWP 12.


In order to qualify for nationwide permit authorization,
proposed activities must meet a number of general
conditions, as well as permit-specific restrictions. One of
the general conditions concerns tribal rights: General
Condition 17 states that no authorized activity or its
operation may impair reserved tribal rights, including but
not limited to, reserved water rights and treaty fishing and
hunting rights. (For information on Corps tribal


gognpo               goo
g
               , q
'S
a  X
11LULANJILiN,

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Short-term subscription options include 24 hours, 48 hours, or 1 week to HeinOnline.

Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most