H. Rept. 115-154 1 (2017-06-02)

handle is hein.congrecreports/crptxaaca0001 and id is 1 raw text is: AUTHENTICATEO
U.S. GOVERNMENT
INFORMATION
       GP













                     115TH CONGRESS                                            REPORT
                         1st Session    HOUSE OF REPRESENTATIVES               115-154







                         TO AUTHORIZE THE EXPANSION OF AN EXISTING
                       HYDROELECTRIC PROJECT, AND FOR OTHER PURPOSES



                       JUNE 2, 2017.-Committed to the Committee of the Whole House on the State of
                                         the Union and ordered to be printed



                       Mr. BISHOP of Utah, from the Committee on Natural Resources,
                                            submitted the following


                                               REPORT

                                               [To accompany H.R. 220]

                                [Including cost estimate of the Congressional Budget Office]

                       The Committee on Natural Resources, to whom was referred the
                     bill (H.R. 220) to authorize the expansion of an existing hydro-
                     electric project, and for other purposes, having considered the
                     same, report favorably thereon with an amendment and rec-
                     ommend that the bill as amended do pass.
                       The amendment is as follows:
                       Strike all after the enacting clause and insert the following:
                     SECTION 1. TERROR LAKE HYDROELECTRIC PROJECT UPPER HIDDEN BASIN DIVERSION AU-
                             THORIZATION.
                       (a) DEFINITIONS.-In this section:
                           (1) COMMISSION.-The term Commission means the Federal Energy Regu-
                         latory Commission.
                           (2) TERROR LAKE HYDROELECTRIC PROJECT.-The term Terror Lake Hydro-
                         electric Project means the project identified in section 1325 of the Alaska Na-
                         tional Interest Lands Conservation Act (16 U.S.C. 3212), and which is Federal
                         Energy Regulatory Commission project number 2743.
                           (3) UPPER HIDDEN BASIN DIVERSION EXPANSION.-The term Upper Hidden
                         Basin Diversion Expansion means the expansion of the Terror Lake Hydro-
                         electric Project as generally described in Exhibit E to the Upper Hidden Basin
                         Grant Application dated July 2, 2014, and submitted to the Alaska Energy Au-
                         thority Renewable Energy Fund Round VIII by Kodiak Electric Association, Inc.
                       (b) AUTHORIZATION.-The licensee for the Terror Lake Hydroelectric Project may
                     occupy not more than 20 acres of Federal land to construct, operate, and maintain
                     the Upper Hidden Basin Diversion Expansion without further authorization of the
                     Secretary of the Interior or under the Alaska National Interest Lands Conservation
                     Act (16 U.S.C. 3101 et seq.).
                       (C) SAVINGS CLAUSE.-The Upper Hidden Basin Diversion Expansion shall be sub-
                     ject to appropriate terms and conditions included in an amendment to a license
                     issued by the Commission pursuant to the Federal Power Act (16 U.S.C. 791a et
                     seq.), including section 4(e) of that Act (16 U.S.C. 797(e)), following an environ-
                         69-006

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most