B-294818 1 (2004-12-30)

handle is hein.gao/gaocrptappo0001 and id is 1 raw text is: 




A         G    A    O                                                   Comptroller General
.       Accountability * Integrity * Reliability                         of the United States
United States Government Accountability Office     DOCUMENT FOR PUBLIC RELEASE
Washington, DC 20548                                   The decision issued on the date below was subject to a
                                                       GAO Protective Order. This redacted version has been
                                                       approved for public release.

          Decision

          Matter of: ProTech Corporation

          File:        B-294818

          Date:        December 30, 2004

          Patrick S. Hendrickson, Esq., for the protester.
          Derek D. Crick, Esq., Preston Gates Ellis, for Atherton Construction, Inc., the
          intervenor.
          Roger Christopher Paden, Esq., Department of the Army, and John W. Klein, Esq.,
          and Kenneth Dodds, Esq., Small Business Administration, for the agencies.
          Charles W. Morrow, Esq., and Guy R. Pietrovito, Esq., Office of the General Counsel,
          GAO, participated in the preparation of the decision.
          DIGEST

          Selection of higher-rated, higher-priced proposal over lower-rated, lower-priced one
          was unreasonable, where the weight applied to the evaluation factors in the source
          selection decision differed from that announced in the solicitation.
          DECISION

          ProTech Corporation protests the award of a contract to Atherton Construction, Inc.
          under request for proposals (RFP) No. W912DQ-04-R-0015, issued by the U.S. Army
          Corps of Engineers, for the construction of military family housing.

          We sustain the protest in part and deny it in part.

          The RFP provided for the award of fixed-price contract for construction services
          described as a Site Adapt/Design Build of 62 new military family housing units,
          consisting of 30 duplexes and two single story detached units. The construction
          project was divided into three phases, which the contractor was required to perform
          in the following sequence: phase one -- design and optional fast-track construction;
          phase two -- construction of new family housing units; and phase three - demolition
          of existing family housing units. See RFP at 1, 202. With respect to phase two, the
          RFP advised that [t]he contractor will not be allowed to start construction of any
          portion of any housing unit, including its foundation until all main utilities are

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most