About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline

B-415035 1 (2017-11-08)

handle is hein.gao/gaobadtzu0001 and id is 1 raw text is: 



GO U.S. GOVERNMENT ACCOUNTABILITY OFFICE
441 G St. N.W.                                                  Comptroller General
Washington, DC 20548                                            of the United States
                                         .......................................................................................................................
                                            DOCUMENT FOR PUBLIC RELEASE
                                          The decision issued on the date below was subject to
Decision                                  a GAO Protective Order. This redacted version has
                                          been approved for public release.


Matter of:  Geotech Environmental Services, Inc.

File:        B-415035

Date:        November 8, 2017

Nancy M. Camardo, Esq., and Justin T. Huffman, Esq., Camardo Law Firm, PC, for the
protester.
Alexis J. Bernstein, Esq., and Christopher S. Cole, Esq., Department of the Air Force,
for the agency.
Pedro E. Briones, Esq., and Peter H. Tran, Esq., Office of the General Counsel, GAO,
participated in the preparation of the decision.
DIGEST

Protest that agency was required to seek further clarification before rejecting the
protester's proposal as unacceptable is denied where the agency identified a material
omission from the protester's technical proposal during discussions but the protester's
final revised proposal did not address the omission.
DECISION

Geotech Environmental Services, Inc., a small business located in Addison, Illinois,
protests the rejection of its proposal and the award of a contract to Wadsworth
Builders Company, Inc., of Great Falls, Montana, under request for proposals (RFP)
No. FA4626-16-R-0032, issued by the Department of the Air Force to construct water
wells at Malmstrom Air Force Base (AFB), Montana. Geotech challenges the evaluation
of its technical proposal and contends that the Air Force's exchanges with Geotech
were flawed.

We deny the protest.

BACKGROUND

The RFP was set aside for small businesses and provided for award of a fixed-price
contract on a lowest-price, technically-acceptable basis, considering technical, price,
and past performance evaluation factors. Agency Report (AR), Tab 3, RFP at 17, 35,
45-46. The procurement was conducted using Federal Acquisition Regulation (FAR)
part 15 procedures and offerors were advised that the Air Force would hold discussions

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most