B-404847.6 1 (2012-01-25)

handle is hein.gao/gaobadooq0001 and id is 1 raw text is: 




          G    A     O0                                                  Comptroller General
Accountability * Integrity * Reliability                                 of the United States
  United States Government Accountability Office    DOCUMENT FOR PUBLIC RELEASE
  Washington, DC 20548                                The decision issued on the date below was subject to
                                                      a GAO Protective Order. This redacted version has
                                                      been approved for public release.
           D  e c i s i o n                          L .-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - . . . . ..


           Matter of:  Advanced Construction Techniques, Inc.

           File:       B-404847.6

           Date:       January 25, 2012

           Barbara G. Werther, Esq., Paul M. Vincent, Esq., Christian F. Henel, Esq., and
           Jackson B. Boyd, Esq., Ober, Kaler, Grimes & Shriver, for the protester.
           Michael A. Branca, Esq., Lori Ann Lange, Esq., and Aaron Brotman, Esq., Peckar &
           Abramson, PC, for Bauer Foundation, Corp., an intervenor.
           Michelle F. Barczak, Esq., and Thomas M. Browder, III, Esq., Department of the
           Army, Corps of Engineers, for the agency.
           Susan K. McAuliffe, Esq., and Edward Goldstein, Esq., Office of the General
           Counsel, GAO, participated in the preparation of the decision.
           DIGEST

           1. Protest of agency's technical evaluation is denied where protester fails to show
           that weaknesses attributed to its proposal were unreasonable.

           2. Notwithstanding the lack of a specific price realism evaluation factor, source
           selection authority's (SSA) best-value tradeoff decision properly questioned whether
           protester's low price was realistic, where the solicitation provided for the
           evaluation of an offeror's understanding of technical requirements, as well as an
           assessment of the risks associated with an offeror's proposal, and the SSA
           concluded that protester's low price appeared to stem directly from specific
           concerns regarding the protester's lack of technical understanding and risks
           inherent in its proposal.
           DECISION

           Advanced Construction Techniques, Inc. (ACT), of Wilmington, Delaware, protests
           the award of a contract to Bauer Foundation Corp., of Edessa, Florida, under
           request for proposals (RFP) No. W912P5-09-R-001 1 issued by the Department of
           the Army, Corps of Engineers for the construction of a barrier wall at Center Hill
           Dam, Dekalb County, Tennessee. ACT contends that the agency unreasonably
           evaluated its proposal, failed to conduct meaningful discussions with ACT regarding
           cited weaknesses in its proposal, and made an unreasonable and improper best-
           value award decision.

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most