B-198204 1 (1980-05-01)

handle is hein.gao/gaobadifr0001 and id is 1 raw text is: 

                   LLR r
                STHE COMPTROLLER GENERAL
  DECISION      .       .=OF   THE   UNITED STATES
                          WASHINGTON, D.C. 20548



  FILE:  B-198204               DATE: May 1, 19b0

  MATTER  OF:   Department of the Treasury,
                Customs Service

  DIGEST:

     Since Government agency did not mail
     acceptance of bid to contractor prior
     to expiration of period of availability
     for obligation of fiscal year 1979 appro-
     priation, no binding agreement within
     meaning of 31 U.S.C. § 200(a) (1976)
     arose in fiscal year 1979 which would
     provide basis for recording obligation
     against fiscal year 1979 appropriation
     and, therefore, fiscal year 1980 funds
     must be used.

     The Department of the Treasury, Customs Service,
 e uest  a decision regarding the propriety of recording
 an oB igation in fiscal year 1979 (FY 79) where the docu-
 ment providing the basis for the obligation was misplaced
 due to an apparent distribution error and not discovered
 until the following fiscal year. A brief summary of
 the circumstances reported follows.

     The obligation relates to a procurement for con-       V
struction of certain employee residences. The project
was identified as an FY 79 requirement, the project cost
was included in Customs Financial Plan, and the project
was approved on March 1, 1979. Invitation for bids
(IFB) No. CS-79-42 was issued on August 9, 1979, and
bids were opened on September 10, 1979. Gerrico Con-
struction Inc. (Gerrico) submitted the low, responsive
bid.  During the week of September 17, 1979, the presi-
dent of Gerrico was telephonically informed that his
bid had been accepted and that award would be made to
Gerrico.  On September 22, 1979, Customs assigned FY 79
contract number Tc-79-54 to the Gerrico contract.
On September 28, 1979, the contracting officer signed
SF 23 (Construction Contract) which by reference incor-
porates the Gerrico signed bid. Upon signing the
document, the contracting officer immediately relin-
quished control over it by placing it in the Customs

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most