B-185572 1 (1976-08-03)

handle is hein.gao/gaobaddjd0001 and id is 1 raw text is: 




                            C' THE COMPTROLLER GENERAL
*DECISION                        4    OF   THE UNITED STATES
                            5'        WASHINGTON, D.C. 20548

                                    -Q  LM9~

         FILE:  B-185572                    DATE:      August 3, 19T6

         MATTER OF: Fattore Construction Company


         DIGEST:

         1.   Bidder's failure to complete appendix A, containing
              Washington Plan, by signing certificate and inserting
              goals, renders bid submitted in connection with grant
              award nonresponsive and may not be corrected or waived
              as a minor informality or irregularity, even though
              bid was signed and only applicable trade involved
              $4,000 of $1,298,125 bid.

         2.   Terms of Washington Plan contemplate commitment of
              minority hiring by prime contractor and imposition of
              such commitment upon subcontractors; therefore sub-
              contracting of work for only applicable trade does
              not permit correction or waiver of prime's failure
              to make commitment.


              Fattore Construction Company (Fattore) has filed a complaint
         against the rejection of its bid by the Washington Suburban
         Sanitary Commission (WSSC). The procurement, which involves the
         construction of a portion of the Anacostia River relief sewer
         system, is funded in substantial part (75 percent) by a grant
         from the Environmental Protection Agency (EPA) pursuant to title
         II of the Federal Water Pollution Control Act Amendment of 1972,
         Public Law 92-500.

              On August 19, 1975, 12 bids were received and opened. The
         apparent low bidder was Fattore with a bid of $1,298,125. The
         second low bid of $1,336,345 was submitted by Charlep F. Smith &
         Son, Inc. (Smith).  Addendum No. 1 to the invitation for bids
         (IFB) required bidders to fully complete appendix A, which
         contained the Washington Plan for minority hiring. Fattore
         failed to enter a minority percentage goal for electricians
         required for the performance of the contract and also failed to
         sign appendix A.  On October 9, 1975, the WSSC rejected Fattore's
         bid for failure to properly fill out and execute appendix A.




                        .- 1 -

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most