B-201390 1 (1980-12-30)

handle is hein.gao/gaobabjxy0001 and id is 1 raw text is: 
                          4b
          w,  :                                       /-7-71


GAO
United States General Accounting Office            Office of
Washington, DC 20548                               General Counsel
                                                   In Reply
                                                   Refer to: B-201390


   G'R, A Partnership
   1804 Dante Street
   New Orleans, LA   70118

        Attention: Marco J. Giardino, Principal
                    Partner

   Gentlemen:

        We refer to your November 25, 1980 letter protesting
   the award of contract J7530-0-0024 by the National Park Ser-
   vice, Department of the Interior, to the Center for Gulf South
   History for an ethnohistoric overview of Mississippi Delta
   culture.

        The enclosures to your letter show that you were advised
   of the selection of the Center for Gulf South History on
   August 1, 1980, and of the specific reasons therefor by letter
   from the contracting officer dated August 13. On August 15,
   you sent to the contracting officer a notice of appeal and
   complaint to the General Services Administration Board of
   Contract Appeals protesting the award; we assume that you
   expected that the notice of appeal would be forwarded to
   the referenced body. However, your letter was treated by the
   contracting officer as a protest to the procuring activity,
   and the protest was denied by letter of September 22. We
   received your November 25 letter on December 1.

        Section 20.2(a) of our Bid Protest Procedures, 4 C.F.R.
   part 20 (1980), requires that a protest against a contract
   award be filed in either the contracting agency or the General
   Accounting Office within 10 working days after the basis for
   protest is known or should have been known, whichever is
   earlier. (The contracting agency may impose a more stringent
   time for filing a protest with it, which will control when
   that alternative is selected by a disappointed bidder or
   offeror.) The section also requires that when a protest has
   been timely filed with a contracting agency, any subsequent
   protest to our Office be filed within 10 working days of
   knowledge of the agency's initial adverse action on the
   matter.





     3                          Ki 2

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most