About | HeinOnline Law Journal Library | HeinOnline Law Journal Library | HeinOnline

GAO-02-898R 1 (2002-07-24)

handle is hein.gao/gaobaamam0001 and id is 1 raw text is: 


   I


       Accountability * Integrity * Reliability
United States General Accounting Office
Washington, DC 20548



         July 24, 2002


         The Honorable Tom Harkin
         The Honorable Charles E. Grassley
         The Honorable Peter G. Fitzgerald
         The Honorable Richard Durbin
         United States Senate

         The Honorable Lane Evans
         The Honorable James A. Leach
         The Honorable Jim Nussle
         House of Representatives

         Subject: 2002 Update of the 155 mm Lightweight Howitzer

         In July 2000 and April 2001, we issued reports to you and several other members of
         Congress describing the schedule, cost, and technical status of the 155 mm
         Lightweight Howitzer program.' The 155 mm Lightweight Howitzer is expected to
         replace the M-198 towed howitzer. The Army-Marine Corps Lightweight Howitzer
         Joint Program Office is directing this program's development, with BAE SYSTEMS
         (BAE), a British company, as the prime contractor.

         This report responds to your request of February 27, 2002, that we continue to
         monitor and report on this program due to your continued concerns about its
         schedule, cost, and technical difficulties and the program's readiness for low-rate
         initial production.

         Results in Brief

         Since our April 2001 report, all key milestones have slipped in large part because a
         2-year low-rate initial production phase has been added to the program to provide
         production representative howitzers for operational testing. Correspondingly, the
         full-rate production decision has slipped from September 2002 to October 2004. The
         initial fielding of the howitzer by the Marine Corps has slipped to March 2005 or 8
         months. The initial fielding of the howitzer by the Army has slipped to August 2006,
         or 17 months.

         'See U.S. General Accounting Office, Status Update of the New 155 mm Lightweight Howitzer, GAO-
         01-603R (Washington, D.C.: Apr. 10, 2001) and Defense Acquisitions: Howitzer Program Experiencing
         Cost Increases and Schedule Delays, GAO/NSIAD-00-182 (Washington, D.C.: July 28, 2000).


GAO-02-898R 155mm Lightweight Howitzer

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most