GAO-02-642R 1 (2002-05-23)

handle is hein.gao/gaobaalzk0001 and id is 1 raw text is: 


   £


      Accountability * Integrity * Reliability
United States General Accounting Office
Washington, DC 20548


         May 23, 2002

         The Honorable Dan Burton
         Chairman
         Committee on Government Reform
         House of Representatives

         Subject: NASA Contract Payments

         Dear Mr. Chairman:

         You asked us to determine whether the National Aeronautics and Space
         Administration (NASA) had significant problems with overpayments to its
         contractors. The objectives of our review were to (1) survey contractors and vendors
         to determine whether NASA had made significant payment errors on its contracts and
         purchase orders and (2) review the design of NASA's controls to prevent, detect, and
         correct payment errors.

         We selected 110 contracts and purchase orders on which NASA had made $4.8 billion
         in payments during the first 9 months of fiscal year 2001 (the most recent data
         available at the time). During those 9 months, NASA had disbursed about $8.7 billion
         on 6,815 contracts and purchase orders. By the end of fiscal year 2001, NASA
         disbursed almost $11.7 billion on 8,141 contracts and purchase orders, of which about
         $11.5 billion pertained to the contracts and purchase orders included in the 9-month
         population from which we made our selection.

         For the survey, we selected the 10 contracts and 10 purchase orders with the highest
         total disbursements for the 9-month period and random samples of 45 contracts and
         45 purchase orders. NASA disbursed about $6.3 billion during fiscal year 2001 on
         these 110 contracts and purchase orders. For the selected items, we asked the
         contractors and vendors to identify payments that were more than or less than the
         amounts they had billed NASA during the year, with the exception of advances and
         properly calculated progress payments.' Our survey was intended to identify whether
         NASA had a significant problem with payment errors but not to project the amount or
         number of errors to NASA's payment population. For our random samples, one or
         more payment errors reported to us in the survey would indicate a significant or
         systemic problem during the review period. For the 20 largest contracts and purchase
         orders, the dollar amounts of reported errors would have to be evaluated individually


         'Under certain circumstances, the Federal Acquisition Regulation authorizes reductions in progress
         payments, which can be paid in advance of work being accepted. Therefore, we did not consider any
         reduced progress payments as underpayments.


GAO-02-642R NASA Contract Payments

What Is HeinOnline?

HeinOnline is a subscription-based resource containing thousands of academic and legal journals from inception; complete coverage of government documents such as U.S. Statutes at Large, U.S. Code, Federal Register, Code of Federal Regulations, U.S. Reports, and much more. Documents are image-based, fully searchable PDFs with the authority of print combined with the accessibility of a user-friendly and powerful database. For more information, request a quote or trial for your organization below.



Contact us for annual subscription options:

Already a HeinOnline Subscriber?

profiles profiles most